TWIN OTTER

N726JM


Day 1,   Day 2,   Day 3,   Day 4,   Day 5,   Day 6,   Day 7,   Day 8,   Day 9,   Day 10,   Day 11,  
Day 12,   Day 13,   Day 14,   Day 15,   Day 16,   Day 17,   Day 18,   Day 19,   Day 20,   Day 21,  
Day 22,   Day 23,   Day 24,   Day 25,   Day 26,   Day 27,   Day 28,   Day 29,   Day 30,   Day 31,  
Day 32,   Day 33,   Day 34,   Day 35,   Day 36,   Day 37,   Day 38,   Day 39,   Day 40,   Day 41,  
Day 42,   Week 6,   Week 7,   Week 8,   Week 9,   Week 10,   Week 11,   Week 12,  

Day 1
Tuesday November 28th, 2006

Received aircraft late in the afternoon, unloading started immediately and was completed in 1 1/2 hours.

Propellers were sent to the Prop Shop.

DSC01209.jpg


DSC01194.jpg


DSC01196.jpg


DSC01203.jpg


DSC01247.jpg

DSC01212.jpg


DSC01226.jpg


DSC01215.jpg


DSC01240.jpg


DSC01256.jpg


DSC01260.jpg


DSC01270.jpg


DSC01282.jpg


DSC01290.jpg


DSC01313.jpg


DSC01320.jpg



DSC01328.jpg

Return To Top


Day 2
Wednesday November 29th, 2006

Inventory of parts was started and general cleaning commenced.


DSC01345.jpg



DSC01371.jpg


DSC01372.jpg


DSC01374.jpg


DSC01375.jpg


DSC01376.jpg


DSC01379.jpg


DSC01381.jpg


DSC01383.jpg


DSC01391.jpg



Return To Top

Day 3
Thursday November 30th, 2006

Inventories were performed, cleaning continued and inspections began.

DSC01415.jpg


DSC01420.jpg


DSC01429.jpg


Return To Top

Day 4
Friday December 1st, 2006

Inspections continued, parts were shipped for overhaul, new parts were ordered and assembly began.


DSC01450.jpg


DSC01451.jpg


DSC01452.jpg


DSC01459.jpg


DSC01461.jpg



Return To Top

Day 5
Saturday December 2nd, 2006

Parts were moved and cleaned, inspections and inventories continued.


DSC01419.jpg


DSC01472.jpg


DSC01168.jpg


Day 6
Sunday December 3rd, 2006

We rested!


Return To Top

Day 7
Monday December 4th, 2006

Parts ordering, inspections and assembly continued.


DSC01242.jpg


DSC01441.jpg


DSC01509.jpg


DSC01541.jpg


Return To Top

Day 8
Tuesday December 5th, 2006

Parts ordering, inspections and assembly continued.  Wires cleaned and tested.


DSC01508.JPG


DSC01233.JPG


DSC01495.JPG


DSC01324.JPG


Return To Top

Day 9
Wednesday December 6th, 2006

Overall repair, assembly and wire repair.


DSC01468.jpg


DSC01469.jpg


DSC01470.jpg


DSC01471.jpg


DSC01475.jpg


DSC01478.jpg


DSC01479.jpg


DSC01480.jpg


DSC01481.jpg



Return To Top

Day 10
Thursday December 6th, 2006

General assembly and repairs continued along with main gear assembly.


DSC01486.jpg


DSC01488.jpg



DSC01523.jpg


DSC01527.jpg


DSC01528.jpg


DSC01531.jpg


DSC01517.jpg



DSC01508.jpg


DSC01540.jpg


Return To Top

Day 11
Friday December 8th, 2006

Wiring, interior work and overall assembly continued.  A.D. modifications and nose strut restoration after the overhaul were started.  Both left and right wings were installed.

DSC01542.jpg


DSC01546.jpg


DSC01548.jpg


DSC01549.jpg


DSC01585.jpg


DSC01588.jpg


DSC01590.jpg


DSC01596.jpg


DSC01606.jpg


DSC01570.jpg


DSC01573.jpg


DSC01576.jpg


DSC01605.jpg


DSC01616.jpg


Return To Top

Day 12 and 13
Saturday December 9th and Sunday December 10th, 2006

We rested!


Return To Top

Day 14
Monday December 11th, 2006

Cosmetic cleaning and painting, fuel cell preparation, ongoing assembly and preparation work for de-ice boot installation.

DSC01621.jpg


DSC01620.jpg


DSC01619.jpg


DSC01638.jpg


DSC01623.jpg

Return To Top


Day 15
Tuesday December 12th, 2006

Propellers came back from the Prop Shop.  Work continued on the cockpit along with general repairs, cleaning and painting and preparation for further assembly.


DSC01642.jpg


DSC01643.jpg


DSC01655.jpg


DSC01680.jpg


DSC01654.jpg


DSC01665.jpg


DSC01667.jpg


DSC01675.jpg


A1678.jpg


Return To Top

Day 16
Wednesday December 13th, 2006

Completed fuel tank installation and wiring and engineering control cables. 
Completed wing root wiring.

DSC01649.jpg


DSC01670.JPG


DSC01673.JPG

DSC01676.JPG


Return To Top


Day 17
Thursday December 14th, 2006

Refurbishment of cockpit doors.
Replaced upper fuselage with new skin center sheet.
Work continues on general assembly.

DSC01658.JPG


DSC01656.jpg


DSC01679.JPG




Day 18
Friday December 15th, 2006

Hung flight controls and ailerons.
General refurbishment and assembly continues.
Horizontal stabilizer repairs and applicable A.D's complied with.

DSC01699.JPG


DSC01702.JPG


DSC01686.JPG


DSC01703.JPG


Return To Top


Day 19 and 20
Saturday 16th and Sunday 17th December 2006

We rested!


Return To Top


Day 21
Monday 18th December 2006

General refurbishment, assembly and A.D. work continues.

DSC01720.jpg


Return To Top

Day 22
Tuesday 19th December 2006

Work on cockpit gauges.

12 19 01717.jpg


12 19 01718.jpg



Day 23
Wednesday 20th December 2006

General installation and assembly.

000_0296.jpg


DSC01803.jpg



Day 24
Thursday 21st December 2006

Cleaning, preparations for further assembly and hydraulic system work.

DSC01744.jpg


DSC01801.jpg


DSC01802.jpg



Day 25
Friday 22nd December 2006

Interior work continues.

DSC01808.jpg


DSC01809.jpg


DSC01811.jpg



Days 26-30
Saturday 23rd - Wednesday 27th December 2006

We celebrated the holidays and rested.


Return To Top


Day 31
Thursday 28th December 2006

Preperation for further assembly continues.

Friday 29th December 2006

Further assembly and work on the ailerons.

DSC01740.jpg


DSC01783.jpg



Days 33 - 36
Saturday 30th December 2006 - Tuesday 2nd January 2007

We celebrated the New Year and rested!


Return To Top


Day 37
Wednesday 3rd January 2007

Work on the tail section commenced.


1 3 0295.jpg


1 3_0287.jpg


1 3_0288.jpg

Day 38
Thursday 4th January 2007

Work on the tail section continues. 
Work on the engines begins.

DSC01741.jpg


DSC01745.jpg



DSC01743.jpg


DSC01786.jpg


Day 39
Friday 5th January 2007

Building engine up for iinstallation.
Assembly work continues.





DSC01784.jpg

DSC01791.jpg

1 8 1742.jpg

Days 40 - 41
Saturday 6th, Sunday 7th January 2007

We rested.

Return To Top

Day 42
Monday 8th January 2007

Engines were hung.  Assembly work continued.


1 8 1800.jpg


1 8 1812.jpg


1 8 1804.jpg


1 8 1810.jpg


Week 6
Tuesday 9th January 2007 to Monday 15th January 2007

Wing tips prepared for installation.  General assembly and work on the engine air intake.

1 9 1721.jpg


1 9 1806.jpg


1 9 1792.jpg



Return To Top


Week 7
Tuesday 16th January 2007 to Monday 22nd January 2007

Wiring work, fabriaction of new interior.  General assembly continues.


Window Frames.jpg


Interior A.jpg


Interior B.jpg


Interior C.jpg


Door Frame.jpg


Return To Top

Week 8
Tuesday 23rd January 2007 to Monday 29th January 2007

Interior and wiring work continues this week along with ongoing work and final hook ups on the engines.

Engine A.jpg


Engine Side.jpg


Engine intake.jpg


Eingine Close.jpg


Engine Cowling.jpg


Plane hanger.jpg


Window Frame.jpg


Return To Top

Week 9
Tuesday 30th January 2007 to Monday 5th February 2007

Interior work continues throughout this week.  Wing tips installed and engine work continues.

Glass in window.jpg


Inside Windows.jpg


Interior E.jpg


Side Interior D.jpg


Door .jpg


N 726JM is rolled out for engine checks.

Outside C.jpg


Outside B.jpg


Outside A.jpg



Week 10
Tuesday 6th February 2007 - Monday 12th February 2007

Wiring and interior work continue and the windscreen was replaced.
On successful completion of the test flights early this week N726JM left for the Paint Shop on Wednesday 7th.

Interior.jpg


Otter Door.jpg


Windscreen.jpg


Outside.jpg



A Interior from Front.jpg



A Interior from rear.jpg


Ready To Go.jpg


On The Runway.jpg


And Away close up.jpg


And Back.jpg 


Return To Top

Week 11
Tuesday 13th - Monday 19th February 2007

At the Paint Shop


Week 12
Tuesday 20th - Monday 26th February 2007

N726JM returned from the Paint Shop on Saturday 24th February.

A Near Side.jpg


A Off Side.jpg


A Tail.jpg
Return To Top
Login
 
As an example of the distinguished Rolex watch, durable, accurate replica omega watches travel time is a name, but this week calendar type series on the dial with calendar window can display a fake rolex written all week, week display is also available in a variety of languages to choose from, which makes it in function and innovation and breakthrough the heads of replica watches state, and then with a watchband type 950 platinum is perfect, so this table has become the watch market darling.